Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7,8 UGT, STP, COMMERCIAL-A |
Sub Structure Work |
100% |
|
2 |
AGANWADI & COMMUNITY CENTRE, COMMERCIAL - B |
Sub Structure Work |
100% |
|
3 |
External Development |
Sub Structure Work |
30% |
|
4 |
Fire Tank |
Sub Structure Work |
30% |
|
5 |
1,2,3,4,5,6 |
Super Structure Work |
100% |
|
6 |
7,8 |
Super Structure Work |
95% |
|
7 |
UGT, STP |
Super Structure Work |
99% |
|
8 |
Anganwadi & Community Centre |
Super Structure Work |
20% |
|
9 |
Commercial A |
Super Structure Work |
35% |
|
10 |
Commercial B |
Super Structure Work |
20% |
|
11 |
1,2,3,4 |
Finishing Work |
45% |
|
12 |
5 |
Finishing Work |
35% |
|
13 |
6 |
Finishing Work |
25% |
|
14 |
7,8 |
Finishing Work |
10% |
|
15 |
UGT |
Finishing Work |
85% |
|
16 |
STP |
Finishing Work |
75% |