Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7,8 UGT, STP, COMMERCIAL-A, AGANWADI & COMMUNITY CENTRE, COMMERCIAL - B, VCB Room & Meter Room |
Sub Structure Work |
100% |
|
2 |
External Development |
Sub Structure Work |
70% |
|
3 |
Fire Tank |
Sub Structure Work |
80% |
|
4 |
1,2,3,4,5,6 |
Sub Structure Work |
100% |
|
5 |
7,8 |
Super Structure Work |
100% |
|
6 |
7,8 |
Super Structure Work |
96% |
|
7 |
UGT, STP |
Super Structure Work |
99% |
|
8 |
ESS |
Super Structure Work |
70% |
|
9 |
Anganwadi & Community Centre |
Super Structure Work |
70% |
|
10 |
VCB Room & Meter Room |
Super Structure Work |
90% |
|
11 |
Commercial A |
Super Structure Work |
80% |
|
12 |
Commercial B |
Super Structure Work |
20% |
|
13 |
External Development |
Super Structure Work |
30% |
|
14 |
1,2 |
Finishing Work |
85% |
|
15 |
3,4,5,6 |
Finishing Work |
80% |
|
16 |
7 |
Finishing Work |
55% |
|
17 |
8 |
Finishing Work |
45% |
|
18 |
UGT |
Finishing Work |
85% |
|
19 |
STP |
Finishing Work |
80% |
|
20 |
External Development |
Finishing Work |
40% |