Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7,8 UGT, STP, COMMERCIAL-A, AGANWADI & COMMUNITY CENTRE, COMMERCIAL - B, VCB Room & Meter Room, Fire Tank |
Sub Structure Work |
100% |
|
2 |
1,2,3,4,5,6, UGT, STP, COMMERCIAL-A, AGANWADI & COMMUNITY CENTRE, VCB Room & Meter Room, |
Super Structure Work |
100% |
|
3 |
7,8 |
Super Structure Work |
96% |
|
4 |
COMMERCIAL-B |
Super Structure Work |
70% |
|
5 |
1 |
Super Structure Work |
90% |
|
6 |
2 |
Finishing work |
90% |
|
7 |
3 |
Finishing work |
90% |
|
8 |
4 |
Finishing work |
90% |
|
9 |
5 |
Finishing work |
90% |
|
10 |
6 |
Finishing work |
90% |
|
11 |
7 |
Finishing work |
80% |
|
12 |
8 |
Finishing work |
70% |
|
13 |
ESS |
Finishing work |
95% |
|
14 |
UGT |
Finishing work |
95% |
|
15 |
STP |
Finishing work |
95% |
|
16 |
Anganwadi & Community Centre |
Finishing work |
65% |
|
17 |
VCB Room & Meter Room |
Finishing work |
50% |
|
18 |
Commercial A |
Finishing work |
80% |
|
19 |
Commercial B |
Finishing work |
0% |
|
20 |
External Development |
Finishing work |
55% |
|
21 |
Fire Tank |
Finishing work |
80% |